The claim

The Cyber Resilience Act moves product security from being a property of a delivery to being a condition of market access. The expensive part of the regulation is not the individual requirements — most of them are reasonable and familiar. The expensive part is that the requirements are checked against your technical documentation, and documentation can only be written about decisions that were actually taken. Anyone who takes up the CRA once the product has been designed will end up describing choices that were never made.

Security by design, in this context, is not a stance. It is the only method that produces the evidence the regulation asks for.

The dates below were checked against the Commission’s own publications in September 2026.

What applies, and from when

Regulation (EU) 2024/2847 entered into force on 10 December 2024 and applies in stages:

  • 11 June 2026 — Chapter IV started to apply. That is the machinery for notified bodies, the independent assessors that certain products must be assessed by before being placed on the Union market.
  • 11 September 2026 — the reporting obligations under Article 14 started to apply. Manufacturers are to report actively exploited vulnerabilities and severe incidents.
  • 11 December 2027 — the regulation applies in full.

The middle date is worth pausing on, because it has already passed. The reporting duty therefore applies today, while the requirements that determine whether the product may be CE marked at all only start to apply in just over a year. The order is not accidental: the Union wanted visibility into what is actually being exploited before it began examining designs.

Reporting goes through ENISA’s platform and follows a timetable of an early warning within 24 hours, a notification within 72 hours and a final report thereafter — within fourteen days for vulnerabilities and within one month for incidents. Anyone manufacturing connected hardware in series should exercise that chain before it is needed, rather than during the weekend when it is.

The obligation after delivery

Security work used to end at delivery. Now that is where the obligation starts.

REPORTINGArt. 14 · since 11 Sep 2026THE FULL REGULATIONRequirements for CE markingTHE FIRST PRODUCT FULLY IN SCOPEBEFOREWork ends at deliveryUNDER THE CRAObligation runs for yearsDESIGNAT LEAST FIVE YEARS FROM LAUNCHOR LONGER202420252026202720282029203020312032203310 DEC 2024In force.11 SEP 2026Reporting, Art. 14.11 DEC 2027Applies in full.DEC 2032Support period floor.
fig. 1The Cyber Resilience Act against the lifecycle of a product. The support period is as a main rule at least five years from placing on the market. Checked against the Commission’s publications in September 2026.

Why the requirements belong in the design

Three of the regulation’s requirements simply cannot be met retrospectively without rebuilding.

The component inventory. Annex I, Part II, point 1 requires the manufacturer to identify and document the product’s components, including by drawing up a software bill of materials in a commonly used, machine-readable format covering at least the top-level dependencies. The Commission may specify the format and elements through implementing acts. An SBOM produced after the fact is a guess about what was built. An SBOM generated in the build chain is a fact about what was built, and the difference shows the first time somebody asks which units contain a particular library.

The support period. The manufacturer shall determine a support period reflecting how long the product is expected to be in use, and as a general rule it shall be at least five years unless the intended use justifies a shorter duration. The end date, including month and year, shall be stated at the time of purchase. That is a commitment to being able to deliver security updates to a unit in the field for five years or more — which presupposes signed updates, device identity, key management and an update path that works on the customer’s network. All of that is architecture, and architecture is decided early.

Vulnerability handling across the lifecycle. The requirement is not that the product be free of defects, but that vulnerabilities be handled effectively throughout the support period. That presupposes knowing which units exist where, at which version, with whom.

At a manufacturer of battery energy storage systems (BESS) taking a product from concept to series production, that realisation shaped the design. Manual security configuration works for a handful of units. At hundreds per year it becomes both a bottleneck in the factory and a source of deviations that nobody discovers until the unit is standing at the customer — and a deviation discovered in the field is by definition a deviation you cannot document. The security platform and the automated rollout were therefore built into the product rather than configured on site.

What to do now

Four things can be started without waiting for harmonised standards.

Decide whether you are a manufacturer, and of what. The regulation covers products with digital elements, and the boundary against components, integrations and software developed in-house for a machine is not obvious. That assessment governs everything else and should be documented.

Set up the reporting path. The obligation already applies. That means a named function, a routine that works outside office hours, and a prepared channel towards ENISA and the national CSIRT.

Let the build chain produce the SBOM. Make it an artefact requirement in the pipeline, versioned alongside the firmware. Top-level dependencies are the floor in the regulation, not the goal — but start there, since the floor has to be demonstrable in any case.

Decide the support period and write down the reasoning. The material behind the assessment belongs in the technical documentation. It is also a commercial decision: the support period has to outlive the product’s contract term, and that question does not belong to engineering alone.

What is difficult

The standards picture is not finished. The harmonised standards that will give presumption of conformity are still being developed, and the supply of notified bodies is being built up. Our assessment as of September 2026 is that anyone waiting for the picture to clear before starting work will run short of time against December 2027 — not because the requirements are unclear, but because design decisions take a long time to change.

A product in series is not an installation. Industrial security has traditionally been about a site you can visit. The CRA is about units that have been sold, sit with unknown customers in several countries, and are not always reachable. Organisations that are good at the first are often uncomfortable with the second, and it shows in who ends up owning vulnerability handling.

The customer can be part of the problem. An OT customer rarely accepts automatic updates. The regulation meanwhile requires that you can deliver security updates. Reconciling the two is design work — separate channels for security and functional updates, the option of approved installation during a maintenance window — and it becomes far harder once the product has been built.

Sub-suppliers decide more than you think. An integrated third-party module with a shorter support period than your own product limits in practice what you can promise. That negotiation happens at component selection, not at CE marking.